Decision map
| What you have | Technique |
|---|---|
| Unweighted, maximize count of jobs | Greedy, sort by end time |
| Weighted (profit), no overlap allowed | DP + binary search (1235) |
| Deadlines, unit time, maximize profit | Greedy by profit + slot assignment (DSU or heap) |
| Deadlines with durations, maximize count | Greedy with max-heap, drop the longest (630) |
| Limited workers/rooms, jobs overlap | Heap of end times or sweep line |
| Cooldowns / idle time between same tasks | Greedy on frequency (621) |
| Ordering to minimize total cost | Exchange-argument sort with a custom comparator |
You’re right that it’s a large area, but one correction to the mental model first: “job sequencing” isn’t one problem with variations. It’s a cluster of scheduling problems that use different techniques, and the two you recalled are actually in different families. Sorting them out is the useful part.
The two you recalled
- 1235 Maximum Profit in Job Scheduling: this is DP (sort by end time, then for each job binary search the last compatible job,
dp[i] = max(skip, profit + dp[prev])). It’s weighted interval scheduling, and greedy fails here because profit breaks the “earliest end time is always safe” argument. - 871 Minimum Number of Refueling Stops: this is greedy with a max-heap (drive as far as you can, and only when stuck, retroactively “take” the biggest fuel station you passed). There’s a DP solution too. It’s an interesting one but isn’t really job sequencing; it shares the “defer a decision, fix it with a heap” mechanic.
So neither is the textbook Job Sequencing with Deadlines (below). The area is wide precisely because different constraints flip the technique.
The decision map: what the problem gives you decides the tool
| What you have | Technique |
|---|---|
| Unweighted, maximize count of jobs | Greedy, sort by end time |
| Weighted (profit), no overlap allowed | DP + binary search (1235) |
| Deadlines, unit time, maximize profit | Greedy by profit + slot assignment (DSU or heap) |
| Deadlines with durations, maximize count | Greedy with max-heap, drop the longest (630) |
| Limited workers/rooms, jobs overlap | Heap of end times or sweep line |
| Cooldowns / idle time between same tasks | Greedy on frequency (621) |
| Ordering to minimize total cost | Exchange-argument sort with a custom comparator |
Families, ranked by interview value
1. Deadline scheduling with a heap (highest value, the real “job sequencing”)
- Course Schedule III (630): sort by deadline, take each course, and if total time exceeds the deadline, drop the longest one taken so far via max-heap. This is the textbook deadline-scheduling problem and it’s a favorite hard-ish greedy.
- Job Sequencing with Deadlines (GfG, your course version): unit-time jobs with profits; sort by profit descending, place each in the latest free slot at or before its deadline. The “find latest free slot” step can be a linear scan, or a DSU (union a used slot with the one before it) for near-O(1). That DSU trick links directly to your DSU note.
- Maximum Number of Events That Can Be Attended (1353): sort by start, heap of end times, always attend the event ending soonest.
- IPO (502): same “heap of currently available options” shape.
2. Weighted interval scheduling: DP (high value)
- Maximum Profit in Job Scheduling (1235): the template.
- Maximum Earnings From Taxi (2008), Maximum Number of Events That Can Be Attended II (1751, at most k events) are the same DP with a variation.
- Two Best Non-Overlapping Events (2054): sort plus a running max, a light version.
3. Resource allocation: heap or sweep line (high value)
- Meeting Rooms II (253), Meeting Rooms III (2402)
- Car Pooling (1094), My Calendar I/II/III (729, 731, 732)
- Minimum Number of Refueling Stops (871)
- The shared idea: overlapping intervals compete for limited resources, and a min-heap of end times (or a difference array) tracks who’s free.
4. Cooldown / frequency scheduling (medium-high value)
- Task Scheduler (621), Reorganize String (767), Rearrange String k Distance Apart (358)
- Greedy on the most frequent task; the formula-vs-heap solutions are both worth knowing.
5. Ordering for minimum cost: exchange-argument sorts (medium value, high learning value)
- Sort by a comparator that you derive by swapping two adjacent items and asking which order is cheaper.
- Largest Number (179), Minimum Number of Refueling Stops (871) conceptually, Minimum Time to Finish All Jobs (1723, backtracking, a contrast case)
- Classic textbook cousins: minimize total weighted completion time (sort by weight/duration ratio), minimize maximum lateness (sort by deadline, “Earliest Deadline First”). These rarely appear as named LC problems but teach the exchange-argument skill directly.
6. Multi-worker assignment (medium value, harder)
- Minimum Number of Work Sessions to Finish the Tasks (1986, bitmask DP), Find Minimum Time to Finish All Jobs (1723), Parallel Courses III (2050, topological sort with longest path).
- These are typically DP or graph, not greedy, and worth knowing exist rather than drilling.
The transferable mental steps
Most of this area reduces to a short checklist:
- Is there a profit or weight? If yes and jobs can’t overlap, greedy by end time fails, so think DP.
- Is there a deadline? If yes, sort by deadline and use a heap to undo the worst choice made so far (630).
- Are there limited resources? Sweep line or heap of end times.
- Do only the order and cost matter? Derive a comparator via an exchange argument.
The recurring greedy upgrade is the heap as an undo button: take everything tentatively, and when a constraint breaks, remove the worst item taken. You’ve seen it in Furthest Building (1642), 871, and 630.
Where to spend time
If you have limited time: 630, 1235, 253, 1353, 621, plus the textbook deadline version from your course. That covers deadline greedy, weighted DP, resource allocation, and event attendance. Category 6 can wait.
Suggested drill order
- Job Sequencing with Deadlines (your course version): understand the slot-assignment idea, then try the DSU speedup
- Non-overlapping Intervals (435): confirm the unweighted end-time greedy
- Maximum Profit in Job Scheduling (1235): see exactly why greedy breaks with profits
- Course Schedule III (630): the heap-as-undo pattern
- Maximum Number of Events That Can Be Attended (1353)
- Meeting Rooms II (253) → Meeting Rooms III (2402)
- Minimum Number of Refueling Stops (871), as the second heap-as-undo example
- Largest Number (179) for the comparator/exchange-argument skill
One caveat: I’m confident about the technique assignments above, but verify the exact constraints on 1751 and 2054 when you reach them, since I’m summarizing from memory.